US Regulatory Evaluations Detail
Field Evaluation to include the following:
- A comprehensive evaluation of the equipment utilizing the appropriate national and product safety standards (e.g., NFPA 79).
- Internal Technical Peer Review.
- Closing meeting to verbally review list of discrepancy issues at the end of the on-site evaluation.
- An electronic copy of Bullet List Discrepancy Report issued within 3 working days following the On-Site evaluation.
- An electronic copy Final ReportĀ issued within 7 working days following receipt of satisfactory responses to the Bullet List Discrepancy Report.
- A Field Evaluation sticker issued for the equipment having a satisfactory evaluation or reevaluation.
- An approval letter issued to the local Authority Having Jurisdiction (AHJ) issued within 3 working days following the Field Evaluation sticker for the equipment having a satisfactory evaluation or reevaluation.